PROJECT SCHEDULE
PHASE I
- Land selection: October 2015
- Certificate of Public Good approved: December 2015
- Get to full subscription: April 2016
- LLC Operating Agreement and Agency & Lease Agreement: May 2016
- Equipment quotes and firm pricing: May 2016
- Contracts out to members: May 31, 2016
- Detailed design: June 2016
- Groundbreaking: June 7, 2016
- Land preparation complete: June 25, 2016
- Mount installation complete: July 1, 2016
- Installation begin: July 5, 2016
- "Phase One" System online: August 31, 2016
- Full Subscription: July 2018
- Certificate of Public Good approved: September 2018
- Equipment quotes and firm pricing: September 2018
- Contracts out to members: September 2018
- Detailed design: September 2018
- Groundbreaking: October 2018
- "Phase Two" System online: December, 2018