- SCS has entered into a Land Lease Agreement with a local landowner to site the SCS project. See the Project SIte page. This site proved to be ideal, as a Three-Phase electric line passes within 100' of the proposed site, allowing for a full 500kW build-out of the Project on one site.
- A critical number of members has been reached in order to initiate the project permitting process.
- The application for Certificate of Public Good (CPG) has been filed with the Vermont State Public Service Board (PSB).
|