Dear Southshire Community Solar Followers:
We are now on the home stretch and will be beginning construction soon. Here is the tentative schedule:
Certificate of Public Good approval: November 3, 2017. Barring any last minute surprises!
Member Vote-In: November 6, 2017. The current board and membership of SCS LLC would formally vote you Phase 2 prospects as members into the LLC.
SCS Phase II Membership Meeting: November 8, 2017. We will discuss and sign the Solar Contract (between Power Guru and each member-owner), and make the down payments per the schedule in the contract. We will also discuss the LLC Operating Agreement and the Agency & Sub-Lease Agreement (between the LLC and the member-owner). These would be signed by each of you at the McClintock Law Office.
Completion of Land Preparation: November 10, 2017. This is work currently in progress, and involves removal of a dirt pile from Phase I, and construction of erosion and sedimentation control measures, per our site preparation consultants.
Ground Mount Installation: November 13-17, 2017. Solar Foundations, Inc. will be installing the auger driven ground mounts.
Equipment on Site: November 20, 2017.
Solar Installation: November 20, 2017 - February 20, 2018. We would be making every effort to speed up this process, but we are heading into winter. So there's no guarantee of completion by year end, which is our goal.
The SCS board comprising Tim Marr, Susan Lambert and Chuck Putney will be emailing you two documents - the LLC Operating Agreement and the Agency & Sublease Agreement.
Finally, I'm currently working on final design and pricing. As you know, module prices have been trending up lately, due to the ITC tariff expected to be enforced on Chinese imports. These will have a ripple effect on modules from all manufacturers. I'm working with several distributors to get the best pricing. Will keep you informed of the final pricing, soon.
We are now on the home stretch and will be beginning construction soon. Here is the tentative schedule:
Certificate of Public Good approval: November 3, 2017. Barring any last minute surprises!
Member Vote-In: November 6, 2017. The current board and membership of SCS LLC would formally vote you Phase 2 prospects as members into the LLC.
SCS Phase II Membership Meeting: November 8, 2017. We will discuss and sign the Solar Contract (between Power Guru and each member-owner), and make the down payments per the schedule in the contract. We will also discuss the LLC Operating Agreement and the Agency & Sub-Lease Agreement (between the LLC and the member-owner). These would be signed by each of you at the McClintock Law Office.
Completion of Land Preparation: November 10, 2017. This is work currently in progress, and involves removal of a dirt pile from Phase I, and construction of erosion and sedimentation control measures, per our site preparation consultants.
Ground Mount Installation: November 13-17, 2017. Solar Foundations, Inc. will be installing the auger driven ground mounts.
Equipment on Site: November 20, 2017.
Solar Installation: November 20, 2017 - February 20, 2018. We would be making every effort to speed up this process, but we are heading into winter. So there's no guarantee of completion by year end, which is our goal.
The SCS board comprising Tim Marr, Susan Lambert and Chuck Putney will be emailing you two documents - the LLC Operating Agreement and the Agency & Sublease Agreement.
Finally, I'm currently working on final design and pricing. As you know, module prices have been trending up lately, due to the ITC tariff expected to be enforced on Chinese imports. These will have a ripple effect on modules from all manufacturers. I'm working with several distributors to get the best pricing. Will keep you informed of the final pricing, soon.